Challenges In High Density Rack Deployments

Rack densities continue to increase as customers look to optimize data center utilization and reduce costs. If you can go from 4 x 5 Kw racks to 1 x 17 Kw rack, why not? The savings in real estate and infrastructure (racks, rack power strips, connectivity) are significant. Back of the envelope calculation gave me [...]

Solving a Lack of Power Feeds for High Density Servers

Background and Challenge Customer is looking to deploy high density racks, 20 servers (possibly more for future growth) per rack. Each server is estimated to consume 1200W per server, split between 2 power supplies. The estimated load per rack is 24kW. Planning to install 2 power strips each rack for A and B feed. Problem [...]