How to Design and Install Infrastructure Under a Tight Deadline

Objective The customer, a Fortune 100 multi platform technology company, was looking to consolidate multiple engineering labs from various locations into a single colocation to allow for expansion in 3 weeks. Scope of Work Design and Installation Working closely with the customer, the Mirapath team designed and installed both the mechanical and electrical infrastructure for [...]

Social Media Powerhouse Saves Big With Cold Aisle Containment

Background and Challenge A large social media company was looking to revise their current cooling and containment design with the goal of achieving a power usage effectiveness (PUE) of 1.2. Some hurdles were encountered throughout the project with the customer being in a colocation space and having no control over fire suppression placement (sprinklers). Shrink [...]

7,500 Copper and Fiber Connections in 20 Days

In a span of 21 days, Mirapath deployed 7,500 copper and fiber connections for a leading eCommerce company. Background and Challenge One of the largest eCommerce companies in the world was building up its colocation site under tight deadlines. The original goal was to have 150 racks deployed along with 300 power strips and 7,500 fiber [...]

Solving a Lack of Power Feeds for High Density Servers

Background and Challenge Customer is looking to deploy high density racks, 20 servers (possibly more for future growth) per rack. Each server is estimated to consume 1200W per server, split between 2 power supplies. The estimated load per rack is 24kW. Planning to install 2 power strips each rack for A and B feed. Problem [...]